ข่าวแจ้งตลาดหลักทรัพย์
09 พฤศจิกายน 2541
UBMITS Y2K STATUS REPORT
Y2K Status Report for SET as at 30 October 1998
Progress report on the Berli Jucker Year 2000 Compliance Project as at 30 October,
1998.
Project Timetable - Berli Jucker
Compliance testing of applications software Status
MIS - Order Processing, Inventory Control, Compliant
Accounts Receivable, and Cost of Goods Testing completed 31/4/98
Payroll / HRM compliance testing Compliant
Testing completed 31/3/98
Oracle OLAP package Already compliant
Operating Systems and database products Already compliant
Examination & correction of spreadsheets Complete by end of December 1998
ORACLE Financial Applications Already complaint
Compliance testing for embedded devices Complete by end of April 1998
Check compliance programs of our trading On-going
partners
Upgrade of PC's and PC software Complete by end of November 1998
Develop contingency plan to cover 1st draft complete.
unforeseen problems internally or with our
trading partners.
Subsidiary Companies
Cellox Paper Company Limited
Cellox have confirmed that their computer hardware and software has been tested and is
compliant. The majority of the manufacturing equipment contains no Programmable Logic
Controllers (PLC) devices. All equipment containing PLC has been tested and is compliant.
Thai Glass
The Thai Glass plans to achieve Y2K compliance are well advanced. Examination and correction
of all manufacturing equipment is complete. The upgrading of computer hardware and software
will be complete by the end of March 1999.
Rubia Industries
An inventory of all manufacturing equipment has been produced. The analysis of these embedded
systems is complete. Upgrades to the MRPII software package and associated computer hardware
are in progress. This will be complete by the end of November 1998.
Thai-Scandic Steel Company Limited
Y2K Compliance testing of all communications and computer systems is complete. Testing and
upgrading of manufacturing equipment containing PLC devices is continuing with the equipment
suppliers.
Thai Fluorspar
Compliance testing for all PC based systems is complete.
Polipharm Company Limited
Polipharm have no manufacturing equipment that contains PLC devices. Existing non-compliant
Personal Computers and associated software are being replaced.
Siam Snack Company Limited
Compliance testing for all PC based systems has been completed. Non-compliant PCs are being
upgraded. An inventory of all manufacturing equipment has been produced. Twelve of the twenty-
one pieces of equipment contain no PLC devices. Siam Snack is working with the suppliers of the
remaining equipment to ensure compliance.
Thai Klinipro Company Limited.
An inventory of all equipment has been completed and the business criticality assessed. The
majority of the manufacturing equipment is simple and does not contain PLC devices. All of the
specialized equipment is compliant. Thai Klinipro are upgrading their accounting and payroll
packages to ensure compliance.
Project Budget & Expenditure
The total budget to achieve Y2K Compliance for Berli Jucker is Baht13, 500,000.
For the period January - July 1998 Baht5, 500,000 has been spent to upgrade and replace essential
computer hardware and software.
A further Baht6, 000,000 will be spent on PC equipment and software by December 1998 to
complete the project.
Risks/Issues
The only outstanding work that is required by Berli Jucker to complete its preparations for Y2K is
the purchase and installation of new personal computers.
Our two major Thai Bankers, Bangkok Bank and The Thai Danu Bank have provided positive
information regarding their respective projects to ensure Y2K compliance.
The only area of concern for Berli Jucker is the level of compliance of our major utility providers.
Although the following organizations are all active in preparing for Y2K there are concerns that
they will have completed the required work on time. These organizations are:
Ministry of Transport
Metropolitan Water Authority
Metropolitan Electricity Authority
Communications Authority
Telephone Organization of Thailand
None of the above have responded to the Berli Jucker questionnaire requesting information
regarding their plans for compliance. While it is believed that most of these organizations will
achieve compliance by the third or forth quarter 1999 this is too late to satisfy the warranty and
certification requirements of many of our trading partners.